PROGRESS UPDATE

Building 1 is progressing well, with the internal fit-out now well underway.

Building 6 has reached a major visual milestone, with external cladding now complete and internal works in full swing.

Building 5 is coming together quickly; Level 1 framing has been installed, cladding is about to begin, and ground floor plastering is now commencing following the completion of internal framing and rough-ins.

Buildings 3 and 4 are tracking similarly, with Level 1 framing now installed. Ground floor framing is complete, and rough-ins are underway, with cladding set to commence in the coming weeks.

And finally, Building 2 has hit a major project milestone, with the final suspended slab successfully poured – marking a key structural achievement for the development.

 