TINA Residences Project Update | May 2025
TINA Residences is now sold out & we’re pleased to share significant progress across the site, with each building moving steadily through their construction milestones.
PROGRESS UPDATE
Building 1 is progressing well, with the internal fit-out now well underway.
Building 6 has reached a major visual milestone, with external cladding now complete and internal works in full swing.
Building 5 is coming together quickly; Level 1 framing has been installed, cladding is about to begin, and ground floor plastering is now commencing following the completion of internal framing and rough-ins.
Buildings 3 and 4 are tracking similarly, with Level 1 framing now installed. Ground floor framing is complete, and rough-ins are underway, with cladding set to commence in the coming weeks.
And finally, Building 2 has hit a major project milestone, with the final suspended slab successfully poured – marking a key structural achievement for the development.