McLaren Estates Project Update | January 2025
January
Development

McLaren Estates Project Update | January 2025

All in-ground services are finished, and kerb and channel works will commence shortly.

Despite delays caused by severe rainfall late last year, practical completion is on track for March 2025*.

Key highlights include:

  • Sold out
  • All in-ground services complete with kerb and channel to commence shortly
  • Delays from initial expected completion date are due to severe rainfall in November and December, resulting in less than 20% productivity

*Subject to external factors, including weather and Toowoomba Regional Council timeframes.