McLaren Estates Project Update | January 2025
McLaren Estates is nearing completion with 80% of the project now complete.
All in-ground services are finished, and kerb and channel works will commence shortly.
Despite delays caused by severe rainfall late last year, practical completion is on track for March 2025*.
Key highlights include:
- Sold out
- All in-ground services complete with kerb and channel to commence shortly
- Delays from initial expected completion date are due to severe rainfall in November and December, resulting in less than 20% productivity
*Subject to external factors, including weather and Toowoomba Regional Council timeframes.