Markwell Estates II Project Update | October 2025
October
Development

Markwell Estates II Project Update | October 2025

  • 28 Lots – Sold Out
  • Bulk earthworks completed.
  • Topsoil repsread on all lots completed.
  • Watermain installation completed.
  • Stormwater approximately 90% complete.
  • Sub-soil drains now commenced.
  • Roads have been boxed out.
  • Road trimming in progress in preparation for sub-grade proof rolling, with key installation to follow.

Check out the latest in our Project Update video.